Why do I get a warning "continuously restrained by precast concrete deck?

Tekla Structural Designer
2022
Tekla Structural Designer
2021
Tekla Structural Designer
2020
Tekla Structural Designer
2019i
Tekla Structural Designer
2019
Tekla Structural Designer
2018i
Tekla Structural Designer
2018
Tekla Structural Designer
2023
Tekla Structural Designer
Precast
validation
warning
continuously
restrained
concrete
deck
Environment
Eurocode

Question

Why do I get a warning "continuously restrained by precast concrete deck"?

 
Image
2017_04_24_09_15_333.png

Answer

The default beam property, which is carried over from the composite beam with profiled metal decking, is that the Top flange is continuously retrained in the construction stage.

This is incorrect for a precast composite beam so a warning is issued if the restraint is NOT set to No, or edited via the Edit dialog > Lateral restraints page (via the right click context menu).

  
Image
2017_04_24_09_15_544.png


 
Image
2017_04_24_09_14_482.png


If you set to No then the validation warning is removed and the construction stage checks in accordance with SCI P401, Cl 4.1.4 Balanced condition, are carried out.

In the Normal stage the beams are always assumed to be fully restrained.